Thank you to everyone who has participated in the engagement process. Phases 1 and 2 of public engagement are now complete. We received helpful input from the community of North Cowichan and the Maple Bay area residents through two open houses and online surveys that have helped to inform a final preferred concept plan.
- Review the Phase 2 Engagement Summary of the input received: What We Heard
First Nations consultation
Following the public engagement phases, North Cowichan staff consulted with Cowichan Tribes on the replacement of the wharf. Feedback was received on building materials, environmental issues, accessibility, reserved moorage and archaeological requirements. This feedback will be incorporated into the final design of the wharf.
Next steps
In 2023 a design brief and conceptual design was developed based on input from Cowichan Tribes and the from what was heard from the public in 2022. The conceptual design includes access to the beach, moorage for small vessels and tenders, a gazebo and 100 meters of vessel parking. The moorage will be a combination of reserved and transient and short term.
Staff budgeted $1.2 million in the 2024 capital budget for the replacement of the wharf. This includes the wharf head, gangway, floats and piles. Wharf lighting and water service (including hydrants) will be part of the final design. The project does not include the upland parking lot area which will be budgeted in a subsequent year.
In July 2024 proposals were received for the final design of the Maple Bay Wharf. The design work will include environmental and archeological investigations and permitting, surveying, geotechnical study and wave study.
As part of the design work, the construction estimate was update to be $2 million. In the 2025 budget process, the additional budget was not approved, so the project was placed on hold. As part of the 2026 budget process, the additional budget will again be requested. If successful, it is anticipated that construction will take place in 2026/2027.
Background
The wharf at Maple Bay is nearing the end of its lifespan. North Cowichan intends to replace the wharf, however it would like to hear from feedback to help inform conceptual designs. The existing facility is primarily used for temporary summer moorage as it is not protected from winter storms.Maple Bay Wharf location map
Survey
Questions
Have a question about the Maple Bay wharf replacement? Ask it here.
To ask a question you must create an account or log in.
These are the people that are listening and responding to your questions.
The Project Team
The Project Team
{{question.description}}